Analysis of Delay Factors Leading to Contract Disputes in Construction Projects: A Case Study of Badung Regency

Main Article Content

I Putu Kresna Suputra Kresna
I Gede Fery Surya Tapa
I Ketut Sutapa

Abstract

In every construction project implementation, what is often a source of problems and disputes is project delays where debates about who and what are the causes and also demands between the owner and the implementer. This study aims to identify the factors causing delays that have the potential to cause disputes. The method used is descriptive statistical analysis. After obtaining the factors causing delays that have the potential to cause disputes, the second stage questionnaire was distributed again to see the level of agreement of each cause of project delays that have the potential to cause disputes. The results of this study found 53 variables that were successfully identified as causes of construction project delays that have the potential to cause disputes. For the results of the factor analysis, it was found that the most dominant factor causing construction project delays that have the potential to cause disputes was the coordination, control and evaluation of work. The coordination, control and evaluation of work factors had the largest percentage variance value among the other formed factors, amounting to 49.914%.

Article Details

How to Cite
1.
Kresna IPKS, Tapa IGFS, Sutapa IK. Analysis of Delay Factors Leading to Contract Disputes in Construction Projects: A Case Study of Badung Regency. telsinas [Internet]. 2026Apr.16 [cited 2026Apr.21];9(1):48-60. Available from: https://journal.undiknas.ac.id/index.php/teknik/article/view/7589
Section
Articles

References

Andi, A., Susandi, S. & Wijaya, H. 2004. On Representing Factors Influencing Time Performance Of Shop-House Constructions In Surabaya. Civil Engineering Dimension, 5, Pp. 7-13.

Assaf, S. A. 1995. Causes Of Delay In Large Building Construction Projects. Journal Of Management In Engineering, 11, 45-50.

Astina, D. C. N., Widhiawati, I. A. R. & Joni, I. G. P. 2012. Analisis Faktor-Faktor Penyebab Keterlambatan Pelaksanaan Pekerjaan Proyek Konstruksi Di Kabupaten Tabanan. Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil, 1.

Ervianto, W. I. 2005. Manajemen Proyek Konstruksi. Yogyakarta. Andi Ofset.

Hansen, S. 2015. Manajemen Kontrak Konstruksi, Gramedia Pustaka Utama.

Latief, Y. 2001. Perencanaan dan Penjadwalan Konstruksi. Jakarta : Universitas Indonesia.

Nurasiyah. 2009. Kontrak Kerja Konstruksi.

Poerdyatmono, B. 2009. Alternatif Penyelesaian Sengketa Jasa Konstruksi. Jurnal Teknik Sipil Universitas Atma Jaya Yogyakarta, 8, Pp. 78-90.

Proboyo, B. 2004. Keterlambatan Waktu Pelaksanaan Proyek Klasifikasi Dan Peringkat Dari Penyebab-Penyebabnya. Civil Engineering Dimension, 1, Pp. 46-58.

Rusman, M. & Malahayati, N. 2012. Faktor-Faktor Resiko Yang Mempengaruhi Kinerja Waktu Pelaksanaan Konstruksi Gedung Secara Swakelola (Studi Kasus: Proyek Pengembangan Sekolah Menengah Kejuruan Di Provinsi Aceh). Jurnal Teknik Sipil, Pascasarjana Universitas Syiah Kua La, 1, 97-111.

Sianipar, H. B. 2012. Analisis Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Konstruksi Pengaruhnya Terhadap Biaya. 8-9.

Soeharto, I. 2005. Manajemen Konstruksi. Jakarta: Penerbit Bina Ilmu.

Sugiyono, P. D. 2010. Metode Penelitian Pendidikan. Pendekatan Kuantitatif.

Supranto, J. 2010. Prosedur Penelitian, Suatu Pendekatan Praktek. Edisi Revisi Iv. Jakarta. Penerbit Renika Cipta.

Yasin, I. H. N. 2004. Mengenal Klaim Konstruksi & Penyelesaian Sengketa Konstruksi, Gramedia Pustaka Utama.

Yuliana, C. 2016. Faktor-Faktor Potensial Terjadinya Perselisihan Kontrak Pada Proyek Gedung. Info-Teknik, 5, 7-17.

Hair, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2010). Multivariate Data Analysis (7th ed.). Upper Saddle River, NJ: Pearson Prentice Hall.

Abiyati, H. & Rani, H. A. 2017. Analisis Faktor-Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung di Kabupaten Aceh Barat. Jurnal Teknik Sipil dan Teknologi Konstruksi, 3(1), Pp. 12-24.

Famiola, M. & Arisundani. 2011. Faktor-Faktor Penyebab Sengketa (Dispute) pada Kontrak Konstruksi di Indonesia. Jurnal Manajemen Teknologi, 10(1).

Giri, I. B. P. & Widhiawati, I. A. R. 2014. Identifikasi Faktor-Faktor Penyebab Perselisihan (Dispute) pada Proyek Konstruksi di Bali. Jurnal Ilmiah Elektronik Infrastruktur Teknik Sipil, 3(1).

Idrus, A. & Sodangi, M. 2010. Framework of Communicative Determinants for Contract Disputes in Construction Projects. Journal of Applied Sciences, 10, Pp. 3058-3064.

Kaming, P. F., Olomolaiye, P. O., Holt, G. D. & Harris, F. C. 1997. Factors Influencing Construction Time and Cost Overruns on High-Rise Projects in Indonesia. Construction Management and Economics, 15, Pp. 83-94.

Messah, Y. A., Widodo, T. Y. & Kalidome, A. 2013. Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung di Kota Kupang. Jurnal Teknik Sipil, 2(2), Pp. 157-168.

ambasivan, M. & Soon, Y. W. 2007. Causes and Effects of Delays in Malaysian Construction Industry. International Journal of Project Management, 25(5), Pp. 517-526.

Widhiawati, I. A. R. 2009. Analisis Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi di Kota Denpasar. Jurnal Ilmiah Teknik Sipil, 13(2).