Evaluating Contractor Performance through Cost-Time Management Strategies in Educational Building Project

Authors

  • Me Me Maw Mahidol University, Phutthamonthon District, Nakhon Pathom 73170, Thailand
  • Sang Kompiang Rizki Putra Atmaja Universitas Udayana
  • I Wayan Murtika Universitas Pendidikan Nasional

DOI:

https://doi.org/10.38043/telsinas.v8i1.6229

Keywords:

Performance, Contractor Management, Cost Control, Time Efficiency

Abstract

Project performance is a critical indicator in assessing the effectiveness and efficiency of construction projects, particularly in terms of cost and time management. This study aims to analyze the key factors influencing contractor performance in the classroom rehabilitation project in Bali, focusing on cost and time aspects. Data were collected through questionnaires distributed to 30 respondents, including contractors and consultants directly involved in the project. The findings indicate that thorough cost planning, strict budget control, and effective cost risk management significantly contribute to project success. Likewise, realistic scheduling, regular progress monitoring, and inter-team coordination are essential in ensuring timely project delivery. The use of technology and active stakeholder engagement further enhance operational efficiency. These results contribute to strengthening project management strategies, particularly for small-scale educational rehabilitation projects in Indonesia.

References

M. Jahangirian, S. J. Taylor, T. Young, and S. Robinson, Key performance indicators for successful simulation projects, Journal of the Operational Research Society, vol. 68, no. 7, pp. 747765, 2017.

K. O. Obuo and S. P. Nyangau, Project Cost Management Process And Performance Of Road Projects In Nairobi City County, Kenya, International Journal of Social Sciences Management and Entrepreneurship (IJSSME), vol. 8, no. 4, 2024.

I. N. I. Kumara, I. K. A. Ariana, I. G. F. S. Tapa, D. C. Indrashwara, L. P. M. K. Putri, and I. K. A. D. A. Putra, Synergy of Value Engineering and Green Energy Systems in Innovating Building Construction, in 2024 10th International Conference on Smart Computing and Communication (ICSCC), pp. 203207, 2024.

D. Girma, Internal Factors Affecting Contractors Performance and the Improvement Mechanisms: Construction Technology and Management, Ethiopian Journal of Engineering and Technology, vol. 3, no. 1, pp. 128145, 2023.

I. N. I. Kumara, Penerapan Metode Least Cost Analysis Untuk Optimasi Percepatan Waktu Pelaksanaan Proyek, Reinforcement Review in Civil Engineering Studies and Management, vol. 2, no. 1, pp. 824, 2023.

I. Dharmayasa, M. Y. Anggreni, P. Anantanasakul, and I. P. Sugiana, Geotechnical Evaluation of Landslide Risks in Balis Tourism ZonesA Case Study from Candidasa, Bali, Indonesia, Ecological Engineering & Environmental Technology, vol. 25, 2024.

I. K. A. Ariana, N. P. M. S. P. Wirawan, I. N. I. Kumara, and I. K. Nuraga, Characteristics and Analysis of Factors Affecting the Performance of Service Providers (Contractors) in Denpasar City in 2023, Formosa Journal of Science and Technology, vol. 3, no. 10, pp. 22552270, 2024.

M. Ershadi, M. Jefferies, P. Davis, and M. Mojtahedi, Modeling the capabilities of high-performing project management offices in general contracting companies, Project Management Journal, vol. 54, no. 3, pp. 268284, 2023.

I. N. I. Kumara, I. G. F. S. Tapa, D. C. Indrashwara, I. W. D.Pancane, & M. A. Predana, Value Engineering in Enhancing Green Building Innovation, Journal of Geoscience, Engineering, Environment, and Technology, vol.10, no 1, pp. 64-70, 2025.

A. Kumar and Y. Hooda, Assessing Cost Overrun in Construction Industry: A Review, in International Conference on Structural Engineering and Construction Management, pp. 561576, Cham: Springer Nature Switzerland, June 2024.

N. R. Vyas, Future of risk-based monitoring in clinical trials, International Journal of Clinical Trials, vol. 7, no. 3, pp. 221228, 2020.

I. K. A. Ariana, D. A. P. A. G. Putri, and M. D. C. Boavida, Analisa Deskriptif Keterlambatan Pekerjaan Proyek Konstruksi Eto Tower Dili, Timor-Leste, Jurnal Ilmiah Telsinas Elektro, Sipil dan Teknik Informasi, vol. 5, no. 2, pp. 105111, 2022.

F. Sarifah, N. Fauziah, S. Evana, R. Pertiwi, A. Z. Fadhlurrahman, and R. Nugraha, Kontribusi PTPP Terhadap Sustainable Development Goals Pada Tahun 20202022, Jurnal Ilmiah Telsinas Elektro, Sipil dan Teknik Informasi, vol. 7, no. 1, pp. 1428, 2024.

P. Gbahabo and A. O. Samuel, Effects of infrastructure project cost overruns and schedule delays in sub-Saharan Africa, in 11th International Conference on Social Sciences, Helsinki, pp. 2021, Jan. 2017.

M. S. Ab Rahim, G. Reniers, M. Yang, and P. Siwayanan, Integrating Process Safety and Process Security Risk Management: Practitioner Insights for a Resilience-Oriented Framework, Processes, vol. 13, no. 2, article 392, 2025.

T. K. I. Adham and A. Sukkar, Effective Management of Construction Project Team: Identifying Leadership Qualities and Responsibilities, Scholars Journal of Economics, Business and Management, vol. 11, no. 2, pp. 6373, 2024.

A. Rashidi, D. W. Chan, M. Ravanshadnia, H. Sarvari, and A. Tajaddini, Applying building information modelling (BIM) technology in pre-tender cost estimation of construction projects: a case study in Iran, Buildings, vol. 14, no. 5, article 1260, 2024.

R. Wang, D. A. S. Samarasinghe, L. Skelton, and J. O. B. Rotimi, A study of design change management for infrastructure development projects in New Zealand, Buildings, vol. 12, no. 9, article 1486, 2022.

A. Ribeiro, A. Amaral, and T. Barros, Project Manager Competencies in the context of the Industry 4.0, Procedia Computer Science, vol. 181, pp. 803810, 2021.

F. Slaeat, The impact of poor planning on the duration and cost of the projects: The implications of poor planning on the projects, Mesopotamian Journal of Civil Engineering, pp. 6081, 2024.

T. Ahmad, J. Boit, and A. Aakula, The role of cross-functional collaboration in digital transformation, Journal of Computational Intelligence and Robotics, vol. 3, no. 1, pp. 205242, 2023.

I. Vreko, P. Tominc, and K. irec, Enhancing the performance of high-growth small-and medium-sized enterprises through effective project-management processes and stakeholder engagement: a systems perspective, Systems, vol. 11, no. 10, article 511, 2023.

G. Dimech, R. D. Gonzi, and A. Wild, Multi-dimensional Modelling for Mapping Project Trade-offs in Construction: A Maltese Perspective, in Managing Risk and Decision Making in Times of Economic Distress, Part A, vol. 108, pp. 5167, Emerald Publishing Limited, 2022

Downloads

Published

2025-04-17

How to Cite

1.
Maw MM, Putra Atmaja SKR, Murtika IW. Evaluating Contractor Performance through Cost-Time Management Strategies in Educational Building Project. telsinas [Internet]. 2025Apr.17 [cited 2025Apr.21];8(1):58-63. Available from: https://journal.undiknas.ac.id/index.php/teknik/article/view/6229

Issue

Section

Articles